Projects
Lead Partner: Dandara Ltd
Project Team: Alison Gallagher, Mary McBryan, Mark Philp, Derek Young
Website: www.gh2o.co.uk
Project HistoryClick an image to enlarge
Location:
Greater Govan & Glasgow Harbour, Glasgow Harbour
Description:
This inspiring residential development is being constructed in three stages. It comprises five imposing 16-22 storey towers facing the River Clyde, with an eight storey linear block to the north.
A total of 819 apartments will be built, with 95% enjoying river views. Basement parking is also planned along with a ground floor commercial zone at the western edge of the site. Consideration has been given to the integration of both private and public space within and surrounding the development.
Current status:
Stages 1 (282 units) and 2 (205 units) of Phase 2 have been completed. Stage 3 on hold at present.
Timescale:
Stages 1 and 2 completed 2009
Cost:
£85 million